Iteration and release planning · Question 4 of 60
What does iteration planning deal with?
1 answer is correct. Easy Created with AI
Show answer
Answer
- D With the iteration backlog up to the end of one iteration
Explanation
Iteration planning covers just one iteration and works with that iteration's backlog.