ISTQB CTFL
Test planning and estimation
Easy
Test plan
Iteration and release planning
Entry and exit criteria
- What do entry criteria define?
- What are exit criteria often called in agile development?
- What is a typical entry criterion?
- What do exit criteria define?
Estimation techniques
- What data does estimation based on ratios use?
- Which three values does three-point estimation use?
- Which technique is a variant of Wideband Delphi common in agile teams?
- For which lifecycles is extrapolation particularly suitable?
- Why are large tasks broken down into smaller ones before estimating?
Test case prioritisation
- Which test cases run first in risk-based prioritisation?
- Who defines requirement priorities in requirements-based prioritisation?
Test pyramid
- What are tests in the bottom layer of the test pyramid like?
- Which three layers does the original test pyramid model have?
Testing quadrants
Medium
Test plan
Iteration and release planning
- How do testers contribute to release planning?
- Which tasks do testers take on in iteration planning?
Entry and exit criteria
- Which examples are typical exit criteria?
- What is likely if entry criteria are not met?
- Under what condition may testing end because time or budget has run out?
- For what should entry and exit criteria be defined?
Estimation techniques
- In earlier projects the ratio of development to test effort was 5 : 2. The development effort of a new project is estimated at 750 person-days. What test effort results?
- Experts estimate a test task at 4 hours optimistic, 7 most likely and 16 pessimistic. What is the three-point estimate E = (a + 4m + b) / 6?
- A team needed 18, 22 and 20 person-days of test effort in the last three iterations. What estimate for the next iteration does a simple extrapolation by average give?
- How does Wideband Delphi work?
Test case prioritisation
- Which test case prioritisation strategies are commonly used?
- What must be considered in the execution order besides priorities?
- What happens in coverage-based prioritisation?
Test pyramid
- Which statements apply to higher layers of the test pyramid?
- What does the test pyramid model help a team with?
Testing quadrants
Hard
Estimation techniques
- For test execution experts estimate a = 10, m = 16 and b = 34 person-days. What estimate with standard deviation SD = (b – a) / 6 results?
- A three-point estimate gives E = 7 hours. The experts named a = 3 and b = 15. Which value did they give as most likely (m)?
- In a company test effort has so far been 25% of the total effort for development and testing. A new project expects 900 person-days of development. What test effort results?
- A team estimates using Planning Poker; three people show 5, one shows 21. What is the next step?
- Which statements about the estimation techniques are correct?
- What advantage does three-point estimation offer over a single number?
- A company has no project data of its own and takes the ratio of development to testing from an industry article. Which statements are correct?
Test case prioritisation
- Test cases: T1 low priority, T2 high priority and requiring a customer record created by T1, T3 medium priority without dependencies. In which order should they run?
- With additional coverage prioritisation the tests cover these requirements: T1 {A, B, C, D}, T2 {A, B, E}, T3 {E, F}, T4 {C}. T1 runs first. Which test comes next?
- A load generator is only available on Tuesdays, and the related performance tests have medium priority. What follows for the execution schedule?
Entry and exit criteria
- Which exit criteria are binary yes/no criteria?
- A team wants to start system testing of a booking platform. Which conditions are sensible entry criteria?
- Two days before release the budget is used up, 92% of planned tests have run and two medium defects are open. How should the decision be made?
- A team defines for user stories: "acceptance criteria are available, dependencies are clarified, test data is obtained." What is this?
Test plan
Test pyramid
- A team has 40 unit tests, 60 integration tests and 400 automated UI tests; the suite runs for three hours. What does the test pyramid model recommend?
- Which statements about the test pyramid are correct?
Testing quadrants
- Assign: a team plans load tests, usability tests with customers, automated component tests and tests of a story's acceptance criteria. Which assignments are correct?
- Which statements about automation in the testing quadrants are correct?