Test plan · Question 50 of 60

A test manager thinks a test plan is not worthwhile because everything changes in the project anyway. Which counterarguments are technically correct?

2 answers are correct. Hard Created with AI

Show answer

Answer

  • C Preparing it forces early thinking about risks, schedule, people and tools
  • D It serves as a means of communication with the team and stakeholders

Explanation

The value also lies in planning itself: it forces thinking through future challenges. A test plan can and should be adapted.