Test case prioritisation · Question 57 of 60

A load generator is only available on Tuesdays, and the related performance tests have medium priority. What follows for the execution schedule?

1 answer is correct. Hard Created with AI

Show answer

Answer

  • B The tests are scheduled on Tuesdays even if higher-priority ones are still pending

Explanation

The execution order must also take into account the availability of tools, environments and people.