Entry and exit criteria · Question 49 of 60
Two days before release the budget is used up, 92% of planned tests have run and two medium defects are open. How should the decision be made?
1 answer is correct. Hard Created with AI
Show answer
Answer
- A Stakeholders assess the residual risk and decide whether to accept it for release
Explanation
Running out of time or budget can be a valid exit criterion if stakeholders have reviewed and accepted the risk; the report must show open items.