Estimation techniques · Question 43 of 60
In a company test effort has so far been 25% of the total effort for development and testing. A new project expects 900 person-days of development. What test effort results?
1 answer is correct. Hard Created with AI
Show answer
Answer
- D 300 person-days
Explanation
25% test of the total means development : test = 75 : 25 = 3 : 1. With 900 development days that is 900 / 3 = 300 test days. 225 would be 25% of development alone.