Estimation techniques · Question 58 of 60
A company has no project data of its own and takes the ratio of development to testing from an industry article. Which statements are correct?
2 answers are correct. Hard Created with AI
Show answer
Answer
- C The estimate should be communicated openly together with its assumptions
- D Its own historical data would be the better source
Explanation
Ratios from one's own earlier projects are best suited. Every estimate rests on assumptions and is subject to error, which stakeholders must understand.