Estimation techniques · Question 30 of 60
A team needed 18, 22 and 20 person-days of test effort in the last three iterations. What estimate for the next iteration does a simple extrapolation by average give?
1 answer is correct. Medium Created with AI
Show answer
Answer
- D 20 person-days
Explanation
(18 + 22 + 20) / 3 = 20 person-days; this is a simple form of extrapolation from measurements of the current project.