Estimation techniques · Question 30 of 60

A team needed 18, 22 and 20 person-days of test effort in the last three iterations. What estimate for the next iteration does a simple extrapolation by average give?

1 answer is correct. Medium Created with AI

Show answer

Answer

  • D 20 person-days

Explanation

(18 + 22 + 20) / 3 = 20 person-days; this is a simple form of extrapolation from measurements of the current project.