Estimation techniques · Question 28 of 60
In earlier projects the ratio of development to test effort was 5 : 2. The development effort of a new project is estimated at 750 person-days. What test effort results?
1 answer is correct. Medium Created with AI
Show answer
Answer
- C 300 person-days
Explanation
750 / 5 × 2 = 300 person-days.