Estimation techniques · Question 28 of 60

In earlier projects the ratio of development to test effort was 5 : 2. The development effort of a new project is estimated at 750 person-days. What test effort results?

1 answer is correct. Medium Created with AI

Show answer

Answer

  • C 300 person-days

Explanation

750 / 5 × 2 = 300 person-days.