Estimation techniques · Question 29 of 60
Experts estimate a test task at 4 hours optimistic, 7 most likely and 16 pessimistic. What is the three-point estimate E = (a + 4m + b) / 6?
1 answer is correct. Medium Created with AI
Show answer
Answer
- A 8 hours
Explanation
(4 + 4 × 7 + 16) / 6 = 48 / 6 = 8 hours.