Test monitoring and completion · Question 9 of 60

When is a test completion report produced?

1 answer is correct. Easy Created with AI

Show answer

Answer

  • D Once a project, a test level or a test type has been completed

Explanation

The completion report is produced at test completion, ideally once exit criteria are met. Progress reports, by contrast, appear regularly.