Risk management · Question 38 of 60

How is the risk level usually determined in the qualitative approach?

1 answer is correct. Medium Created with AI

Show answer

Answer

  • D With a risk matrix

Explanation

Qualitatively the risk level is determined via a matrix of likelihood and impact classes, quantitatively by multiplication.