A test manager wants to know whether testing is on schedule and how good the product is. Which metrics fit?

3 answers are correct. Hard Created with AI

Show answer

Answer

  • A Number of open defects by priority
  • C Share of executed versus planned test cases
  • D Availability and response time in test operation

Explanation

Test progress, defect and product quality metrics show progress and quality.