Test monitoring and completion · Question 59 of 60
A test manager wants to know whether testing is on schedule and how good the product is. Which metrics fit?
3 answers are correct. Hard Created with AI
Show answer
Answer
- A Number of open defects by priority
- C Share of executed versus planned test cases
- D Availability and response time in test operation
Explanation
Test progress, defect and product quality metrics show progress and quality.