Risk management · Question 42 of 60
Risk A: likelihood 0.5, damage €8,000. Risk B: likelihood 0.1, damage €30,000. Risk C: likelihood 0.3, damage €20,000. In which order should they be treated by risk level?
1 answer is correct. Hard Created with AI
Show answer
Answer
- C C, A, B
Explanation
A = €4,000, B = €3,000, C = €6,000. C has the highest risk level, then A, then B.