Risk management · Question 7 of 60

What is a test approach called that selects and prioritises activities based on risk analysis and risk control?

1 answer is correct. Easy Created with AI

Show answer

Answer

  • C Risk-based testing

Explanation

In risk-based testing the selection, priority and management of test activities follow the risks.