Sprint · Question 4 of 12
What applies to the Sprint Goal during the Sprint?
1 answer is correct. Easy Created with AI
Show answer
Answer
- D No changes are made that endanger it
Explanation
Nothing that would put the Sprint Goal at risk is changed during the Sprint. Scope can be renegotiated with the Product Owner; the goal stays.