Sprint · Question 12 of 12
Midway through the Sprint, a stakeholder asks to add an urgent new item. Which statements are correct?
2 answers are correct. Hard Created with AI
Show answer
Answer
- A It must not endanger the Sprint Goal
- C The Product Owner decides how to handle it
Explanation
New requests go to the Product Owner. The scope of the Sprint Backlog can be renegotiated with the Developers as long as the Sprint Goal is not endangered; otherwise the item goes into a later Sprint.