Sprint · Question 9 of 12
A team wants to insert a "planning week" between two Sprints. How should this be judged?
1 answer is correct. Medium Created with AI
Show answer
Answer
- C Not intended; the next Sprint starts immediately
Explanation
A new Sprint starts immediately after the previous one. Preparatory work such as refinement happens within Sprints, not in phases in between.