Sprint · Question 9 of 12

A team wants to insert a "planning week" between two Sprints. How should this be judged?

1 answer is correct. Medium Created with AI

Show answer

Answer

  • C Not intended; the next Sprint starts immediately

Explanation

A new Sprint starts immediately after the previous one. Preparatory work such as refinement happens within Sprints, not in phases in between.