Sprint · Question 10 of 12
What applies to quality during the Sprint?
1 answer is correct. Medium Created with AI
Show answer
Answer
- C It must not decrease
Explanation
Quality does not decrease during the Sprint. If time gets tight, scope is negotiated with the Product Owner rather than relaxing the Definition of Done.