Artifacts in general · Question 3 of 12
Which commitment belongs to the Sprint Backlog?
1 answer is correct. Easy Created with AI
Show answer
Answer
- B The Sprint Goal
Explanation
The Sprint Goal is the commitment of the Sprint Backlog. It gives the Developers a shared objective to align their work with.