Artifacts in general · Question 10 of 12

A team updates its Sprint Backlog only once a week. What is the most likely consequence?

1 answer is correct. Medium Created with AI

Show answer

Answer

  • A The Daily Scrum relies on an outdated picture of the work

Explanation

The Sprint Backlog is a real-time picture of the work in the Sprint. If it is outdated, the transparency needed to inspect progress toward the Sprint Goal in the Daily Scrum is missing.