Artifacts in general · Question 10 of 12
A team updates its Sprint Backlog only once a week. What is the most likely consequence?
1 answer is correct. Medium Created with AI
Show answer
Answer
- A The Daily Scrum relies on an outdated picture of the work
Explanation
The Sprint Backlog is a real-time picture of the work in the Sprint. If it is outdated, the transparency needed to inspect progress toward the Sprint Goal in the Daily Scrum is missing.