At the end of the Sprint, five of eight items are done; three do not meet the DoD. Which steps are correct?

2 answers are correct. Hard Created with AI

Show answer

Answer

  • A The three items return to the Product Backlog
  • C Only the five done items are part of the Increment

Explanation

Only work that meets the Definition of Done is part of the Increment. Undone items return to the Product Backlog, where the Product Owner reorders them. Sprint length and quality remain fixed.