Artifacts in general · Question 2 of 12

Which commitment belongs to the Increment?

1 answer is correct. Easy Created with AI

Show answer

Answer

  • A The Definition of Done

Explanation

Each artifact has a commitment: Product Backlog – Product Goal, Sprint Backlog – Sprint Goal, Increment – Definition of Done.