What does the Kanban practice "limit WIP" mean?

1 answer is correct. Easy

Show answer

Answer

  • C Limiting the number of tasks worked on at the same time in a work step

Explanation

WIP stands for "work in progress". Limits prevent too much being started at the same time. This way tasks are finished faster and bottlenecks become visible. New work is only pulled when capacity is free.