What does the Kanban practice "limit WIP" mean?
1 answer is correct. Easy
Show answer
Answer
- C Limiting the number of tasks worked on at the same time in a work step
Explanation
WIP stands for "work in progress". Limits prevent too much being started at the same time. This way tasks are finished faster and bottlenecks become visible. New work is only pulled when capacity is free.