Agile methods · Question 11 of 12
A Sprint lasts one month. Which maximum durations does the Scrum Guide specify for the events?
1 answer is correct. Hard
Show answer
Answer
- D Sprint Planning up to 8 hours, Sprint Review up to 4 hours, Sprint Retrospective up to 3 hours
Explanation
For a one-month Sprint the Scrum Guide limits the events to 8 hours of Planning, 4 hours of Review and 3 hours of Retrospective, less for shorter Sprints. The Daily Scrum always lasts 15 minutes. The time boxes keep meetings focused.