Agile methods · Question 12 of 12

In the middle of a Sprint a client wants to squeeze in an urgent new feature. How do you proceed according to Scrum?

1 answer is correct. Hard

Show answer

Answer

  • C The Product Owner adds it to the Product Backlog and orders it; the running Sprint is only changed if the Sprint Goal is not endangered

Explanation

New requests go into the Product Backlog, and the Product Owner orders them. The Sprint Goal remains stable; the Sprint Backlog can be adjusted jointly as long as the goal remains achievable. If the Sprint Goal becomes obsolete, only the Product Owner can cancel the Sprint.