Product Backlog · Question 9 of 12

Which aspects can the Product Owner take into account when ordering the Product Backlog?

3 answers are correct. Medium Created with AI

Show answer

Answer

  • B Risks that should be clarified early
  • C Value for users and the organization
  • D Dependencies between items

Explanation

Scrum does not prescribe ordering criteria. Value, risk, dependencies and learning needs are common. The order of arrival says nothing about value, and individual preferences are no yardstick.