Refinement · Question 6 of 12
When does Product Backlog refinement take place?
1 answer is correct. Easy Created with AI
Show answer
Answer
- D Continuously, as needed
Explanation
Refinement is an ongoing activity; during the Sprint the Product Backlog is refined as needed. It is not an event of its own and needs no special Sprint.