Refinement · Question 7 of 12
When is a Product Backlog item considered ready for selection in Sprint Planning?
1 answer is correct. Easy Created with AI
Show answer
Answer
- B When the team can get it done within one Sprint
Explanation
Items that the Scrum Team can get done within one Sprint are deemed ready for selection. They usually acquire this transparency through refinement. Scrum does not require a complete specification.