Lifecycle models and testing · Question 52 of 60

In a project, test analysis for system testing only begins once the system is fully integrated. Which good practice does this violate?

1 answer is correct. Hard Created with AI

Show answer

Answer

  • A Test analysis and design for a test level begin in the corresponding development phase

Explanation

To enable early testing, analysis and design for system testing start already while the system is being specified.