Shift left · Question 48 of 60
A project manager understands shift left to mean that system tests can be dropped because testing happens early. What is correct?
1 answer is correct. Hard Created with AI
Show answer
Answer
- A Shift left brings tests forward, but later testing should not be neglected
Explanation
Shift left means testing earlier, for example without waiting for code or integration. It does not mean omitting later tests.