Lifecycle models and testing · Question 41 of 60

A public-sector project follows the V-model, and code only appears in month seven. What should testers mainly do in the first months?

1 answer is correct. Hard Created with AI

Show answer

Answer

  • C Take part in requirements reviews and advance test analysis and test design

Explanation

In sequential models testers work early on reviews, analysis and design because dynamic testing only becomes possible later.