Test activities and tasks · Question 43 of 60

One week before the deadline only 40% of the tests have been run because the test environment arrived late. Which measures are test control?

3 answers are correct. Hard Created with AI

Show answer

Answer

  • A Adjusting the test schedule to the delayed environment
  • C Reprioritising tests by risk
  • D Scheduling additional testers

Explanation

Comparing with the plan is test monitoring; actions derived from it, such as reprioritising, adjusting the schedule or adding resources, are test control. Simply marking criteria as met would not be legitimate control.