Test activities and tasks · Question 45 of 60
A team is preparing tomorrow's first test run of a payment service. Which activities still belong to test implementation?
3 answers are correct. Hard Created with AI
Show answer
Answer
- A Creating test data and loading it into the environment
- C Checking that the test environment is set up correctly
- E Putting test procedures into a sensible order
Explanation
Providing test data, building and verifying the environment and creating the execution schedule belong to implementation. Comparing results is execution, agreeing objectives is planning.