Test activities and tasks · Question 44 of 60
At the end of a project for a ticketing system three minor defects remain open. Which steps belong to test completion?
3 answers are correct. Hard Created with AI
Show answer
Answer
- A Bringing the test environment into an agreed state
- B Handing reusable test cases over to the maintenance team
- D Creating backlog items for the open defects
Explanation
Open items are transferred, the environment is brought into an agreed state and useful testware is handed over. Open defects belong in the completion report, and testware is kept, not deleted.