Change management · Question 10 of 12

What belongs in an impact analysis before a change?

2 answers are correct. Medium

Show answer

Answer

  • B Which risks to security and availability arise
  • D Which systems, users and processes may be affected

Explanation

The impact analysis clarifies before approval what the change touches and which risks it brings, such as downtime, new attack surfaces or dependent services. The CAB and owners use it to decide whether, when and how to make the change.