Maintenance testing · Question 54 of 60

Two changes are pending: a text correction in a help dialog and a changed interest calculation in loan software. How should the scope of the maintenance tests differ?

1 answer is correct. Hard Created with AI

Show answer

Answer

  • B The interest calculation needs more extensive tests because of higher risk

Explanation

The scope depends on the risk and size of the change and on the system. An interest calculation carries a much higher risk than a help text.