Confirmation and regression testing · Question 30 of 60
How can confirmation testing be done?
2 answers are correct. Medium Created with AI
Show answer
Answer
- A Adding new tests for the changes needed to fix the defect
- B Rerunning all tests that failed because of the defect
Explanation
Depending on risk, failed tests are rerun or new tests are added for the changes. When time is short, at least reproducing the original failure steps is enough.