After a review meeting four severe defects are still open; the exit criteria require zero. What follows in the review process?

1 answer is correct. Hard Created with AI

Show answer

Answer

  • B Create defect reports, follow up corrections and accept the work product only once the exit criteria are met

Explanation

In fixing and reporting, defect reports are created for follow-up; acceptance only comes once exit criteria are reached. A follow-up review may be needed.