Testing principles · Question 42 of 60
For two years a team has run the same manual test suite for a customer management system; it has found nothing for months, yet customers report new failures. Which measures are appropriate?
2 answers are correct. Hard Created with AI
Show answer
Answer
- A Design new tests for the areas affected by customer reports
- C Revise the test data and existing test cases
Explanation
The suite has worn out. Adapted data and new tests help; the old suite can still be useful for regression, but running it unchanged more often will not find anything new.