Why is testing necessary? · Question 49 of 60
After several wrongly calculated delivery dates, analysis shows the developers did not know the public holiday rules of the target countries. What is the root cause here?
1 answer is correct. Hard Created with AI
Show answer
Answer
- B Missing domain knowledge about holiday rules
Explanation
The root cause is the underlying reason for the error, here missing domain knowledge. The calculation in the code is the defect, the wrong date the failure; a missing test case only explains why it was not noticed earlier.