Test design and test implementation with GenAI · Question 37 of 60
Test case B needs a customer created by test case A. What must an execution schedule created by an LLM take into account?
1 answer is correct. Medium Created with AI
Show answer
Answer
- D Schedule A before B, because B needs data from A
Explanation
A dependency fixes the order, regardless of priority. If B runs first, it fails because of missing data rather than a real defect.