Test design and test implementation with GenAI · Question 56 of 60
An LLM schedule puts a high-priority test at the start, although it needs data from another test. What follows from this?
1 answer is correct. Hard Created with AI
Show answer
Answer
- C A dependency was overlooked; the schedule must be corrected
Explanation
A test that needs prepared data cannot run before the test that creates it. Such reasoning errors show why a generated schedule must always be checked.