Risk management · Question 8 of 12

A company drops a risky project because the risk is too high. Which risk treatment is this?

1 answer is correct. Easy

Show answer

Answer

  • B Risk avoidance

Explanation

Avoidance means not carrying out the risky activity. This eliminates the risk completely but also forgoes the potential benefit.