Impediments · Question 11 of 12
The Developers have been waiting for days for test data from another department. Which steps by the Scrum Master are appropriate?
2 answers are correct. Hard Created with AI
Show answer
Answer
- B Clarify with the team whether it can resolve the impediment itself
- C If not, work within the organization to get it removed
Explanation
The Scrum Master causes the removal of impediments. First they enable the team to act itself; what lies outside its influence, they push forward in the organization. Scope is negotiated by the Developers and the Product Owner.