Nexus · Question 12 of 12
At the end of the Sprint, there are only individual team Increments that do not work together. Which statements are correct?
2 answers are correct. Hard Created with AI
Show answer
Answer
- A There is no done Integrated Increment
- D The Nexus Integration Team is accountable for this
Explanation
The goal of a Nexus is at least one done Integrated Increment per Sprint. An Increment is only done when it is integrated, valuable and usable; the Nexus Integration Team is accountable for this.