Stakeholders · Question 8 of 12

How can stakeholders get the Product Backlog changed?

1 answer is correct. Easy Created with AI

Show answer

Answer

  • C By convincing the Product Owner

Explanation

Those wanting to change the Product Backlog must convince the Product Owner. The Product Owner represents the needs of many stakeholders and decides on content and order.