Product Owner accountability · Question 12 of 12

A department head gives the Developers an urgent extra task in the middle of the Sprint, going around the Product Owner. What is the best response in the spirit of Scrum?

1 answer is correct. Hard Created with AI

Show answer

Answer

  • C Pass the request to the Product Owner, who weighs it against Sprint Goal and backlog

Explanation

Anyone who wants to influence the Product Backlog has to convince the Product Owner, who decides whether and where the request fits. Cancelling only makes sense if the Sprint Goal is obsolete, and rejecting the request without weighing it does not help the product.

Certifications & exams

Which exam comes next?

You can already practise for 60 exams, and 7 are up for a vote. See all certifications with their official information, cast your vote or suggest your exam.

See all certifications