Product Backlog · Question 11 of 12

After a merger, there are three lists for the same product: one from sales, one from support and the old IT list, 900 items in total. What should the Product Owner do?

2 answers are correct. Hard Created with AI

Show answer

Answer

  • A Merge the lists into one Product Backlog and remove duplicates
  • C Weed out items that clearly contribute nothing to the Product Goal

Explanation

A product has exactly one Product Backlog, ordered by the Product Owner. Several lists dilute transparency and shift the trade-offs onto the Developers. The Product Owner may remove items without value; refining everything at once, by contrast, would be wasted work.